SILT REMOVAL THROUGH DREDGING WITH REFERENCE TO BALANCING RESERVOIR OF BSL PROJECT

Show simple item record

dc.contributor.author Kumar, Ashok
dc.date.accessioned 2014-10-08T07:05:45Z
dc.date.available 2014-10-08T07:05:45Z
dc.date.issued 2000
dc.identifier M.Tech en_US
dc.identifier.uri http://hdl.handle.net/123456789/4948
dc.guide Chauhan, Gopal
dc.guide Asthana, B. N.
dc.guide Badarinath, H. S.
dc.description.abstract The planning and design of any. Irrigation / Hydroelectric project involve consideration of various parameters so that the system runs at peak efficiency as long as possible. One of the factors, which affects adversely the functioning and -life of any . . project is the silt. Weathering of rocks and disintegration, soil erosion, transportation, depositions are the continuing processes to produce the sediment and to bring it to reservoirs. This problem is more serious with run-of-river hydropower projects. Preventive and curative measures are taken in the form of excluders, ejectors and desilting chambers to reduce adverse impact of silt on electro-mechanical equipments of the power station and their efficiency. These are found effective in removing sediment upto a size of + 0.15 mm. Despite the provision of these measures serious damages to ,equipment have been experienced. These damages are caused due to fine angular quartz particles in the flow of many rivers. Settling tanks of larger size have been found effective in settling fine sediment in tanks. The removal of the settled sediment is a problem in such situations.... en_US
dc.language.iso en en_US
dc.subject WATER RESOURCES DEVELOPMENT AND MANAGEMENT en_US
dc.subject SILT REMOVAL en_US
dc.subject DREDGING en_US
dc.subject BSL PROJECT en_US
dc.title SILT REMOVAL THROUGH DREDGING WITH REFERENCE TO BALANCING RESERVOIR OF BSL PROJECT en_US
dc.type M.Tech Dessertation en_US
dc.accession.number G10124 en_US