Abstract:
Energy is one ofthe most important inputs in the process ofdevelopment for a
nation. With the growth ofindustrialization, there is increase in the demand ofenergy
for trade and commerce on the one hand and demand of transport sector for energy on
the other. As regards the primary sector of Indian economy i.e. agriculture and allied
sectors are concerned, the demand for electricity and Diesel consumption have also
increased on account of increased intensive activities. The domestic energy demand for
meeting fuel and lighting requirements has also increased during the past three decades
on account of rapid increase in population and improvement in the living standard of the
people. After independence large hydro power projects have been executed in India,
some ofthem are still under construction and some have been planned for future. Hydro
power stations have inherent ability for instantaneous starting, stopping and load
variations and also help in improving reliability of power system.
However, economic and environmental factors seriously restrict the exploitation
of hydro power through conventional large capacity projects. Due to these constraints
renewable energy resources such as solar, wind, biomass and small hydro power (SHP),
which India has in abundance are being considered to meet the energy demand in
environmentally benign manner. Among all the renewable energy sources, small hydro
power which is defined by plant capacity up to 25 MW is considered as one of the
most promising source. In India, it has been estimated that apotential of 15,000 MW
exists in small hydro out ofwhich only 2,045 MW has been installed so far.
Large potential of untapped hydro energy is available in flowing streams, river
slopes, canal falls, drainage works and irrigation and water supply dams. Most of
these hydro power sites come under low head range i.e. from 3to 20 m. High head
and medium head small hydro power schemes, are mainly run ofriver schemes. These
schemes are site specific and their installation cost is governed by the cost of civil
works. However, low head schemes are mainly canal based schemes. Run of river in
low terrains and dam toe schemes also considered under low head schemes.
Literature survey reveals that a number of studies have been carried out to
optimise various components of small hydro power specifically. In low head SHP
schemes relatively large discharges are handled, thus size of machines become bigger.
The cost of such projects depend on both civil works as well as electro-mechanical
equipment. It is therefore, there is ascope for cost optimisation for such schemes.
However, no study was reported so far, for cost optimisation of low head small hydro
power installations.
Keeping this in view the present study is carried out covering the following
aspects;
(i) Study of various components of low head small hydro power schemes.
(ii) Carry out the sizing of various components under civil works and selection of
electro-mechanical equipment for different schemes,
(iii) Computation of cost of different components, based on determined sizes for low
headsmall hydro powerschemes,
(iv) Development of correlations for cost of various components for different
schemes under different conditions in order to determine the total installation cost.
(v) Financial analysis for cost optimisation of different schemes based on developed
correlations for cost.
In order to achieve the above objectives, a detailed study of different SHP
schemes and their components has been carried out. There are three types of schemes
under low head hydro power i.e. (i) canal based (ii) run of river and (iii) dam toe. These
schemes have two basic components i.e. civil works and electro-mechanical equipment.
Most of the components are similar in different type of schemes. Out of these, hydro
turbines play an important role which can be said as a heart of small hydro power
station. The type and specification of other components of low head SHP installations
depend upon the type ofhydro turbines as it affects civil works on one side and electrical
equipment on other side.
In the present study, an attempt has been made to develop a methodology for
assessment ofcost ofthe project for determination ofits techno-economical viability
before undertaking detailed investigations, so that only feasible projects are
undertaken for detailed investigations and implementation. The cost of SHP schemes
is site specific, based on type of scheme, type of components, land and infrastructrual
facilities required for execution. The components considered under civil works, were
intake, channel, desilting tank, forebay, penstock and powerhouse building. Various
alternatives under different schemes such as location of power house, type of soil,
type of turbine and generator and number of generating units have been considered
for cost analysis
The sizes of civil works have been determined based on discharge carrying
capacity which is based on head and capacity of the scheme. The head range is
considered from 3 to 20 mand the unit size from 1MW to 5MW with total installed
capacity upto 25 MW for electro-mechanical equipment, turbine and generator are
considered as major equipment. Axial flow turbines i.e. tubular, vertical and bulb type
and type of generator as synchronous and induction have been considered under the
present study. Runner diameter and speed of the turbine have also been determined
based on head and capacity of the scheme.
Based on the correlations developed, installation cost (total project cost) has
been computed for different low head SHP schemes. The total project cost includes
cost ofcivil works, cost ofelectro-mechanical equipment, cost ofmiscellaneous items
in
and other indirect costs. Establishment related cost including designs, audit and
account, indirect charges, tools and plants, communication expenses, preliminary
expenses on report preparation, survey and investigations and cost of land were
considered under miscellaneous and indirect costs. In order to validate the correlation
developed for installation cost a comparison has been made with the actual cost data
of recently developed plants obtained from the developers. Maximum deviation in
cost has been found as±12% for canal based schemes, ±12.5 %in case of run of river
schemes and ±11% for dam toe schemes. The deviation in the costs is considered
within reasonable limits.
It has been found that the electro-mechanical equipment constitute major part
in the cost of low head SHP schemes in canal based schemes. As a typical example,
cost ofelectro-mechanical equipment is found to be 54.5% for aplant having installed
capacity of 2,000 kW at 3mhead and 50.3% at 20 mhead. The similar trend has been
observed in case ofdam toe schemes. However, in case ofrun ofriver scheme, cost of
civil works constitutes major part in total installation cost in higher range ofhead.
Financial analysis has been carried to determine the optimum layout under
different type of schemes based on type of turbines, type of generators and plant load
factor. Different layouts were evaluated for cost optimisation based on installation
cost, generation cost, benefits cost (B-C) ratio, net present value (NPV) and financial
internal rate of return (FIRR).
It is found that these financial parameters follow the same trend for the
optimum layout, leading International financial institutions (World Bank, Asian
development bank) evaluate development projects based on FIRR. Thus FIRR has
been considered as financial parameter to determine the optimum layout.
For atypical canal based scheme of 2,000 kW capacity at 3mhead, tubular
turbine with propeller runner and coupled with induction generator is found optimum
layout as it has minimum installation cost and maximum FIRR value at 90% load
factor. However, for load factors 60%, 70% and 80%, tubular turbine having semi
Kaplan runner coupled with induction generator results in the maximum FIRR values
which is considered as optimum layout. At load factor 50%, bulb turbine with Kaplan
runner coupled with induction generator is found to be the optimum layout as it has
maximum FIRR. It has been found that low head SHP layouts under run of river and
damtoe schemes also follow the similar trend for optimum layouts.
Methodology for determination of optimum installation based on financial
parameters has been employed to compare different alternatives, which can be used
by developers to plan investment in low head SHP schemes. The financers may also
use these cost correlations for appraisal of such schemes for financing.